Air Traffic Management Decisions as “Extraordinary Circumstances”: The General Court’s Judgment in Case T-134/25 and Its Jurisprudential Significance
Have you got a question?
Introduction
In its judgment of 21 January 2026 in Case T-134/25 (ECLI:EU:T:2026:35), the General Court of the European Union clarified the treatment of air traffic management decisions as “extraordinary circumstances” under Article 5(3) of Regulation (EC) No 261/2004. The judgment confirms that such decisions may relieve a carrier of the obligation to pay compensation for a long delay — but only on conditions that the Court was careful to define, and which leave a meaningful boundary in place.
The judgment is also notable for procedural reasons. The dispute was decided by the General Court rather than the Court of Justice because of a recent reform of the EU judicial architecture: under Regulation (EU, Euratom) 2024/2019, with effect from 1 October 2024, jurisdiction to give preliminary rulings in certain defined areas — including compensation and assistance to air passengers — was transferred to the General Court. Consistent with that regime, the reference in this case was lodged with the Court of Justice and transferred to the General Court on 25 February 2025, pursuant to the third paragraph of Article 50b of the Statute. Case T-134/25 is therefore an early and instructive example of how the General Court approaches Regulation 261/2004.
Background to the dispute
The reference arose from proceedings before the District Court, Warsaw, between an air carrier (anonymised in the judgment as “P S.A.”) and the claimant (“D S.A.”), a commercial company to which the passenger had assigned her right to flat-rate compensation. The claimant sought EUR 400 in respect of flight LO 6110 from Izmir (Türkiye) to Warsaw on 25 July 2023, which arrived more than three hours late.
The delay originated upstream in the aircraft’s rotation. The preceding flight (LO 6111, Katowice–Izmir) had been allocated a delayed take-off slot following an Air Traffic Flow Management (ATFM) measure relating to airspace restrictions over Hungary and Romania imposed because of adverse weather. The carrier had signalled that it was ready to depart and requested an earlier departure, but air traffic control did not alter the slot, and the preceding flight arrived in Izmir some 1 hour and 12 minutes late. A separate technical fault discovered after landing in Izmir required a further period of repair. The referring court observed that, if the loss of time attributable to the air traffic management measures were deducted, the final flight’s delay would fall below the three-hour threshold — which is what made the proper classification of the ATFM decision decisive.
The questions referred
The District Court referred four questions, in substance:
- whether every air traffic management decision, irrespective of its duration, is an extraordinary circumstance, even where it does not of itself cause a delay of at least three hours;
- if not, whether the national court must examine the basis of the decision — for example, adverse weather limiting sector capacity — in order to assess whether it amounts to an extraordinary circumstance;
- whether a delay of more than three hours resulting in part from an air traffic management decision imposed on the immediately preceding flight is attributable to an extraordinary circumstance; and
- whether that decision must concern the delayed flight directly, or may concern an earlier flight in the aircraft’s rotation.
The Court’s analysis
The General Court applied the established framework on extraordinary circumstances, as recently restated by the Court of Justice in its judgment of 13 June 2024, D. (Engine design defect), Case C-411/23 (EU:C:2024:498). On that authority, Article 5(3) is a derogation from the principle of compensation and must be construed strictly; a circumstance is “extraordinary” only where two cumulative conditions are met — the event is not, by its nature or origin, inherent in the normal exercise of the carrier’s activity, and it is beyond the carrier’s actual control — with each case assessed on its own facts.
Applying that test, the Court reached three principal conclusions. First, not every air traffic management decision is automatically an extraordinary circumstance; recital 15 of the Regulation does not alter that, because the carrier may itself have contributed to a given decision. Secondly, such a decision is not inherent in the carrier’s normal activity — it is the act of a third party, namely the air traffic management services, and falls within their competence rather than the carrier’s. Thirdly, and decisively, the decision is beyond the carrier’s actual control where the carrier did not contribute to it: the relevant factor is the air traffic management decision itself, which externally affects the flight, rather than the underlying reason for it (here, the weather). The Court emphasised the corollary: where the carrier did contribute — for instance by requesting a new slot on account of its own operational unavailability — the decision is not an event of external origin and cannot found the defence.
The Court also confirmed that an air traffic management decision may qualify even if it does not, of itself, cause a delay of at least three hours. Where a delay has several concurrent causes, the delay attributable to the extraordinary circumstance is deducted from the total in order to determine whether the compensation threshold is reached — a principle drawn from Pešková and Peška (C-315/15).
On the third and fourth questions, the Court held that a carrier may rely on an air traffic management decision that affected an earlier flight operated by the same aircraft, provided two conditions are met: the decision was beyond the carrier’s actual control, and there is a direct causal link between that circumstance and the delay to the subsequent flight — a matter for the national court to verify, having regard in particular to the conditions of operation of the aircraft. Recital 15, the Court noted, ties extraordinary circumstances to a particular aircraft rather than a particular flight, consistent with the rotational-delay case law (Transportes Aéreos Portugueses, C-74/19).
Significance
For carriers, the value of T-134/25 lies less in any enlargement of the defence than in the certainty and structure it provides. The judgment confirms that a binding air traffic management decision — including one affecting an earlier sector in the same aircraft’s rotation — can constitute an extraordinary circumstance, irrespective of its duration or underlying reason, and that the portion of a multi-cause delay attributable to such a decision may be isolated when testing the three-hour threshold. At the same time, by anchoring the analysis in the carrier’s actual control, and by expressly excluding decisions to which the carrier contributed through its own unreadiness, the Court has preserved a real limit: air traffic management cannot be invoked generically to defeat claims where the operative cause lay within the carrier’s sphere.
Read together with C-411/23 on latent technical defects, the judgment helps map the outer boundary of the extraordinary-circumstances defence around events that are genuinely external to, and uncontrollable by, the carrier. It is also an early marker of the General Court’s approach following the 2024 transfer of jurisdiction, and practitioners advising carriers will follow closely how national courts apply the direct-causal-link and actual-control criteria in practice. Our firm advises and represents airlines on the application of Regulation 261/2004, including the assessment and defence of passenger-compensation claims arising from air traffic management constraints and technical disruptions.
Sources: General Court, judgment of 21 January 2026, Case T-134/25, ECLI:EU:T:2026:35; Court of Justice, judgment of 13 June 2024, Case C-411/23, EU:C:2024:498; judgments in Pešková and Peška (C-315/15), Moens (C-159/18) and Transportes Aéreos Portugueses (C-74/19); Regulation (EC) No 261/2004; Regulation (EU, Euratom) 2024/2019.
#AviationLaw #EU261 #ExtraordinaryCircumstances #PassengerRights #GeneralCourt #CJEU #AirlineDefence #ATFM #LegalInsight
- Boulevard "Deshmoret e Kombit", Twin Towers, Tower 1, 13th Floor, 1001, Tirana, Albania
- +355 6969 37763
Book a call back
Share this article
Got a question?
Please complete this form to send an enquiry. Your message will be sent to one member of our team.
Related posts

Air Traffic Management Decisions as “Extraordinary Circumstances”: The General Court’s Judgment in Case T-134/25 and Its Jurisprudential Significance
Introduction In its judgment of 21 January 2026 in Case T-134/25 (ECLI:EU:T:2026:35), the General Court of the European Union clarified the treatment of

Renewable Energy Development in Albania: Legal Framework and Emerging Opportunities
1. Introduction Albania has established itself as a frontrunner in renewable energy development within South-East Europe, leveraging its abundant natural resources and a

Interview with Kai Scholz: Strengthening China-Germany Economic Cooperation in 2025
The year 2025 marks the 50th anniversary of diplomatic relations between China and the European Union, a milestone that highlights five decades of

Stablecoins in the European Legal Order: Regulation, Systemic Risk and the Transformation of Financial Infrastructure (2025 Update)
Stablecoins have evolved from an experimental crypto-instrument into a potential pillar of Europe’s emerging digital financial architecture. With the EU’s Markets in Crypto-Assets